| LA CANADA GYM
Before Harigian Fitness:

facing
gazebo
facing pool

facing tennis
courts
view from old bathroom

previous flooring
DESIGN SKETCHES:

WORK WEEK ONE:
demolish fireplace, kitchen area and
cabinets, stone floor, and wood beams





WORK WEEK TWO:
remove extra bathroom, reroute plumbing,
prep for sub floor, rewire electrical for wide screen plasma TV, and test
paint colors
WORK WEEK THREE: new
drywall, patching and mudding, custom floor arrives, Bella supervises


WORK WEEK
FOUR: new floor laid, prototyping of
new dumbbell rack, Rocky & Charlie (labs) supervise


 
WORK WEEK
FIVE: all equipment is painted and
assembled



WORK WEEK
SIX: equipment packed, shipped, and
assembled in new gym. finishing touches go in.










FINISHED
GYM: 







|