LA CANADA GYM

Before Harigian Fitness:

                               

      facing gazebo                                                         facing pool

                               

                   facing tennis courts                                  view from old bathroom

previous flooring

DESIGN SKETCHES:

       

WORK WEEK ONE:

demolish fireplace, kitchen area and cabinets, stone floor, and wood beams

              

              

              

              

 

WORK WEEK TWO:

remove extra bathroom, reroute plumbing, prep for sub floor, rewire electrical for wide screen plasma TV, and test paint colors

              

              

              

              

                      

 

WORK WEEK THREE:

new drywall, patching and mudding, custom floor arrives, Bella supervises

             

             

             

             

            

 

WORK WEEK FOUR:

new floor laid, prototyping of new dumbbell rack, Rocky & Charlie (labs) supervise

            

            

            

 

WORK WEEK FIVE:

all equipment is painted and assembled

            

            

                     

 

WORK WEEK SIX:

equipment packed, shipped, and assembled in new gym.  finishing touches go in.

          

          

          

          

          

         

         

         

         

           

 

FINISHED GYM:

top of page